Guide
RDSS smart meter installation software and field guide
RDSS (the Revamped Distribution Sector Scheme) is the Government of India's scheme to cut DISCOM losses, with 20.33 crore smart meters sanctioned and 5.73 crore installed by June 2026. AMISPs install and run the meters, usually through installation agencies. This guide explains what that means for field teams, and how installation software like PIEBENCH supports indexing, installation and reporting.
See what’s happening
What RDSS is
The Union Cabinet approved the Revamped Distribution Sector Scheme in June 2021. According to the PIB release, it has an outlay of ₹3,03,758 crore, with estimated gross budgetary support from the Central Government of ₹97,631 crore. REC and PFC were named nodal agencies. The scheme was originally set to run until 2025-26; its sunset date is now 31 March 2028, according to a Ministry of Power reply in Parliament in July 2026.
Its stated objectives were to bring AT&C losses down to 12–15% nationally and to close the gap between the average cost of supply and the average revenue realised (ACS-ARR) by 2024-25. Ongoing work under the earlier IPDS and DDUGJY schemes, and the PMDP-2015 projects for Jammu & Kashmir and Ladakh, was folded into it.
How smart metering works under RDSS
The release describes prepaid smart metering for consumers as "a key feature" of the scheme, to be done in public-private partnership (PPP) mode. Three parts matter for field teams:
- Consumer meters. About 25 crore prepaid smart meters were planned over the scheme period, for all consumers except agricultural connections. The first phase prioritised electricity divisions in AMRUT cities with AT&C losses above 15%, Union Territories, MSMEs and other industrial and commercial consumers, government offices at block level and above, and other high-loss areas.
- System meters. Communicating meters on every feeder and distribution transformer (DT), "to enable energy accounting", also in PPP mode.
- Agricultural connections. Covered through feeder meters rather than individual consumer meters, because of how scattered they are.
The commercial model is TOTEX. As the Prayas Energy Group explains, smart metering projects are executed as a combination of capital and operational expenses, and AMISPs (Advanced Metering Infrastructure Service Providers) are responsible for metering end to end. In practice, an AMISP signs with the DISCOM and then works through installation agencies on the ground.
Where the rollout stands (June 2026)
According to the Ministry of Power's reply in Parliament of July 2026, as reported by T&D India:
- Sanctioned under RDSS: 20.33 crore smart meters, made up of 19.79 crore consumer meters, 52.53 lakh DT meters and 2.05 lakh feeder meters.
- Installed under RDSS: 5.73 crore, as of 30 June 2026. That is about 28% of the sanctioned quantity.
- Installed in India under all schemes: 7.24 crore, including consumer, DT and feeder meters.
Progress has been slower than planned. A year earlier, in a May 2025 analysis of figures as of March 2025, Prayas reported about 13.4 million smart meters communicating and about 4.8 million in prepaid mode. With 14.6 crore sanctioned meters still to install before the 2028 sunset date, the field work is far from finished.
What RDSS asks of field teams
The scheme documents are written for DISCOMs and AMISPs, but most of the obligations land on the person holding the phone at the premises.
Consumer indexing comes first. Energy accounting at feeder and DT level only works if every consumer is mapped to the right DT and feeder. That is a survey job, done before or alongside installation, and errors in it are expensive to find later.
Every installation needs evidence. An old meter removed, its final reading, a new meter with a known serial, seals, the consumer's acknowledgement. Each of these becomes a question at some point, from billing, from audit or from a consumer complaint.
Meters have to communicate, not just be installed. A meter that is on the wall but not reporting to the head-end system (HES) doesn't deliver what the scheme pays for. Non-communicating meters need field visits to diagnose and fix.
Progress has to be reportable. DISCOMs track progress against sanctioned quantities, and the numbers need to hold up when checked.
How installation software maps to it
| RDSS field requirement | What the crew does | How PIEBENCH supports it |
|---|---|---|
| Consumer to DT and feeder mapping | Survey each premises, capture consumer ID, DT, feeder and location | Consumer Indexing template, GPS capture, service points on a map |
| Installation evidence | Record old meter, final reading, new meter, seals, photos, consumer confirmation | Meter Installation template, barcode serials, required photo fields, extra steps added without a developer |
| Data quality | Avoid wrong or duplicate serials | Barcode scanning; duplicate serials refused within a project |
| Review before reporting | Supervisor checks each job | Approval queue with rejection notes; auto-approval rules on Pro |
| Commissioning and NCM | Confirm meters report; visit non-communicating ones | Integration with HES, MDM and billing through Connectorly |
| Crew accountability | Show who worked where and when | Selfie and GPS attendance, stationary-agent detection, audit trail |
| Areas with no network | Keep working without signal | Offline-first Android app that syncs later |
If you run installations under an AMISP, the smart meter installation and AMISP pages go into more detail. Plans start at ₹4,999/month; see pricing.
Built to integrate with your systems
HES, MDM, SAP IS-U, Oracle CC&B and billing systems, over REST, OAuth or a direct SQL connection. How integrations work
Questions buyers ask
What is RDSS in smart metering?
RDSS is the Revamped Distribution Sector Scheme, approved by the Union Cabinet in June 2021 to reduce DISCOM losses. Its smart metering part has 20.33 crore smart meters sanctioned (consumer, DT and feeder meters), implemented in public-private partnership mode through AMISPs. The scheme now runs until 31 March 2028.
What is an AMISP under RDSS?
An AMISP is an Advanced Metering Infrastructure Service Provider. Under RDSS, AMISPs are responsible for smart metering end to end on a TOTEX basis, which combines capital and operating expenses. Most AMISPs work through installation agencies that employ the field crews.
What software do I need for RDSS smart meter installation?
You need a mobile app that works offline and captures consumer indexing and installation evidence (serials, seals, photos, GPS), an approval step before work is reported, and a way to send data to the HES, MDM and billing systems. PIEBENCH covers these in one platform, with templates for indexing and installation.
Why is consumer indexing important under RDSS?
RDSS installs communicating meters on feeders and distribution transformers to enable energy accounting. That accounting only balances if each consumer is mapped to the correct DT and feeder. Indexing errors show up as unexplained losses, which is why indexing is usually done before or alongside installation.
How many smart meters are installed under RDSS?
As of 30 June 2026, 5.73 crore smart meters were installed under RDSS against 20.33 crore sanctioned, according to a Ministry of Power reply in Parliament. Across all schemes, India had 7.24 crore smart meters installed.
Who are the nodal agencies for RDSS?
REC and PFC were nominated as the nodal agencies for implementing the scheme, according to the Cabinet release of June 2021.
Sources